Shenzhen-Zhongshan Link Officially Opens to Traffic
On June 30, the Shenzhen-Zhongshan Link Project, which took 7 years to construct, had been officially completed and opened to traffic. Integrating “bridge, artificial island, tunnel and underwater interchange”, the 24.03km long Shenzhen-Zhongshan Link is the world’s largest cross-sea cluster project. China Railway Shanhaiguan Bridge Group Co., Ltd. and China Railway Baoji Bridge Group Co., Ltd. affiliated to CRHIC have undertaken the steel box girder manufacturing tasks for contract sections G05 and G04 of the Project, including Shenzhen-Zhongshan Bridge (formerly Lingdingyang Bridge), Zhongshan Bridge, non-navigable channel bridge in Hengmen Flood Diversion Zone, non-navigable channel bridge in the West Flood Diversion Zone, non-navigable channel bridge in shallow water area, Wanqingsha Interchange Ramp Bridge and ancillary facilities, with a total length of 7.24 kilometers and a total weight of steel structure of 183,000 tons. The steel box girders adopted in this project are di...
2024
-
06
-
30